The Village / Ownership Briefing
Phase 1 of 5 Day 121 of buildout On schedule

Your project, on demand.

Available at request. Drawn from the systems your team already uses.

Summarize last week's completed project tasks versus what fell behind schedule.

List decisions waiting on approval, ranked by deadline.

Pull the latest schedule and budget status for Building A and the central plaza.

Ask for a summary, anytime.

A short read on what's moved across the project, available the moment you ask Seger.

Phase 1 site work continued ahead of the project baseline through the week, with Buildings A and B both gaining ground against their committed schedules. Building C demolition encountered a six-day hazmat abatement delay, fully absorbed within float, no schedule impact downstream. The monthly draw package closed at $4.2M, on budget, with no flagged variances. Two ownership decisions advanced this week and remain open for your review, listed below.

What's coming up.

The next two weeks at a glance, in one view.

  1. May 05
    Weekly project sync
  2. May 08
    Building A foundation pour begins
  3. May 12
    Phase 1 traffic mitigation review
  4. May 14
    Monthly project review
  5. May 16
    Retail tenant prospect review with brokerage
  6. May 18
    Phase 1 amenity finish package decision due
  7. May 22
    Monthly draw package due

Decisions awaiting approval.

Ranked by deadline, with context attached.

Due May 18

Approve Phase 1 amenity finish package.

Sets amenity finish scope across common areas, fitness, and lobby spaces in Buildings A, B, and C. Package prepared by the development team.

Due May 25

Confirm retail tenant prospect list for pre-leasing kickoff.

Sets the initial retail tenant prospect categories across food and beverage, lifestyle, and experiential for the Phase 1 retail liner. Prepared by the leasing team.